In central Pingtung stand three connected old dormitories, once housing for the Forestry Bureau, their outer walls covered in murals. In April 2026, after a seismic retrofit, they held a reopening event. A news report said the county government’s lease from the National Property Administration ends at the end of next year, leaving roughly a year and a half of operation after the reopening.
A project of more than NT$13 million, set against a year and a half. Both numbers are easy to remember and easy to compare. Before comparing, find the date behind each one.
Three award notices. Line up the dates first
Open the tender search on the Government e-Procurement System. Enter Pingtung County Government as the agency and the district’s Chinese name in the tender title field. Three award notices bear directly on the building itself.
On April 17, 2018 (ROC year 107, as the portal writes it), an environmental improvement project was awarded for a total of NT$11,780,000. On January 15, 2019, a technical services contract for a detailed seismic capacity assessment was awarded for NT$905,000, case number A164-1071221-1. On June 26, 2025, the seismic retrofit was awarded for NT$13,190,000, case number 164-E1140401-2; three firms bid, and the budget was also NT$13,190,000.
Each notice carries two adjacent dates: the award date and the date the award notice was published. The assessment was awarded on January 15 and announced on the 16th; the retrofit was awarded on June 26 and announced on the 27th. When copying, always use the award date, so the dates line up.
Check the unit name as you search. The assessment’s tender notice lists the Labor Affairs Department; the retrofit lists the Department of Labor and Youth Development. Filter by unit name alone and you’ll miss the earlier one. Search by agency name plus tender title and all three appear.
When was the assessment finished?
The video says the assessment was awarded in January 2019, and the artisan district opened seventeen days later. The award date is where a contract starts; on that day, no report has been written yet. The assessment’s award notice gives a performance period of January 15 to March 25, 2019, marked “estimated.” On opening day, the assessment contract had barely begun.
When the report was actually delivered, and what it concluded, isn’t on the procurement portal. That lives in the acceptance records or in the report itself, and you have to request it from the agency.
So the stretch “from assessment to retrofit” can be measured two ways. From the assessment award to the retrofit award is about six years and five months; from the assessment’s estimated completion, about six years and three months. Both can be called “more than six years.” When you write it, put the starting point next to the number.
The subsidy field shows the money. The purpose is elsewhere
The retrofit award notice has a field asking whether the project is subsidized by an agency: subsidizing agency, Ministry of Labor; subsidy amount, NT$9,940,000. Divided by the total award of NT$13,190,000, the subsidy covers about 75.36%, leaving NT$3,250,000. Which budget account covers that gap is in the county’s budget book.
The notice gives only the subsidizing agency and the amount, not the program. The program cited in the video is “Reinforcement and Reconstruction of Hazardous Public Buildings: Vocational Training and Labor Centers,” sourced to the fifth-phase special budget of the Forward-Looking Infrastructure Development Program. Meanwhile, the assessment’s tender title begins “Artisan District: Pingtung County Youth Entrepreneurship Cluster.”
Set the program name beside the tender title and the question stands up on its own: does the use named in the subsidy match the use in the venue’s name? Answering it takes the subsidy approval letter and the original project proposal. How many years the retrofit is expected to serve, and what it is expected to deliver, also have to be found in those two documents.
Months left on the lease: count the denominator yourself
A Commercial Times report on April 2, 2026 says several things: the county leased the site from the National Property Administration for ten years; the lease ends at the end of next year; the park closed for ten months from March last year for the retrofit and reopened early this year; a month of opening events begins April 11; about a year and a half remains after the reopening.
“Reopening” has two dates in the same report: the park reopened early this year, and the opening events began April 11. The ten-month closure runs to the first. Count to April 11 and it comes to more than twelve months. Either number can be written; put its end date beside it.
The time remaining works the same way. From April 11, 2026 to the end of 2027 is about twenty months; a year and a half is eighteen. A two-month difference in the denominator moves the monthly figure: NT$13,190,000 divided by eighteen is about NT$730,000 a month; divided by twenty, about NT$660,000. Whichever one goes in the headline, write its start and end dates beside it.
The retrofit’s own timeline is in the notices too. The first public tender was announced on April 2, 2025 and could not be awarded on April 16; the second was announced on June 2 and awarded on June 26, with a performance period of July 11 to December 8, marked estimated. In the month the park closed, the first tender notice wasn’t online yet.
Make a table, then look at the NT$13 million again
Put the dates in one column and the amounts in another, then add a last column for the source: an award notice, a news report, or a document you still need to request.
April 2018, environmental improvement awarded. January 2019, assessment awarded. February 2019, the district opens. March 2019, the assessment’s estimated completion. March 2025, the park closes. June 2025, retrofit awarded. April 2026, opening events. End of 2027, the lease expires. With eight rows in, the gap from retrofit award to lease expiry is about two and a half years.
This table answers how much was spent, when it was spent and how long is left. Whether the building was dangerous back then waits on the assessment report’s conclusion; whether the lease will be renewed is a question for the lessor, the National Property Administration, and the lessee, the county government. Leave those two cells empty for now, and write where to ask.
Next time you see news about a retrofit project, bring out the table. Which row’s source will you ask about first?
Your turn
Find the award notices for the assessment and the retrofit on the Government e-Procurement System. Which day will you use as “assessment complete”: the award date, the notice date or the estimated completion date of performance? Pick one, give your reason, then recalculate the gap to the retrofit award.
Show hint
The assessment is case A164-1071221-1 and the retrofit is case 164-E1140401-2. The performance period is in the bidder section.
Divide NT$13,190,000 by the report’s “a year and a half,” and by the number of months you count yourself from the reopening to the end of the lease (pick early this year or April 11 as the start, and give your reason). How far apart are the two monthly figures? If only one number can go in the headline, which do you choose, and what words go beside it?
Show hint
The early-year reopening, the April 11 opening events and the lease ending at the end of next year are all in that Commercial Times report. Write the start and end dates first, then divide.
Find another award notice for a Pingtung County project subsidized by the central government, and compare its subsidy ratio with the artisan district retrofit. To confirm whether the subsidy program matches the venue’s actual use, what is the next document you would request? Why that one?
Show hint
Subsidy ratio = subsidy amount ÷ total award amount; both numbers are in the notice’s subsidy field and award data field. The program name is not on the notice.
Sources
- Government e-Procurement System: award notice for the artisan district seismic retrofit (164-E1140401-2, June 27, 2025) ↗
- Government e-Procurement System: award notice for the artisan district detailed seismic capacity assessment (A164-1071221-1, January 16, 2019) ↗
- Government e-Procurement System: award notice for the artisan district environmental improvement project (163-1070323, April 2018) ↗
- Government e-Procurement System: tender search ↗
- Commercial Times: Pingtung artisan district has only a year and a half left to operate (April 2, 2026) ↗